Legal provisions of COM(2022)222 - Amendment of Directives on the promotion of the use of energy from renewable sources, on the energy performance of buildings and on energy efficiency

Please note

This page contains a limited version of this dossier in the EU Monitor.


Article 1 - Amendments to Directive (EU) 2018/2001

Directive (EU) 2018/2001 is amended as follows:

(1) In Article 2, the following point is added:

(9a) ’renewables go-to area’ means a specific location, whether on land or sea, which has been designated by a Member State as particularly suitable for the installation of plants for the production of energy from renewable sources, other than biomass combustion plants.

(2) in Article 3, paragraph 1 is replaced by the following:

‘1. Member States shall collectively ensure that the share of energy from renewable sources in the Union’s gross final consumption of energy in 2030 is at least 45%.’

(3) In Article 15, the following paragraph 2a is inserted:

‘2a. Member States shall promote the testing of new renewable energy technologies in pilot projects in a real-world environment, for a limited period of time, in accordance with the applicable EU legislation and accompanied by appropriate safeguards to ensure the secure operation of the electricity system and avoid disproportionate impacts on the functioning of the internal market, under the supervision of a competent authority.’

(4) The following Article 15b is inserted:

‘Article 15b
Mapping of areas necessary for national contributions towards the 2030 RES target

(1) By [1 year after the entry into force], Member States shall identify the land and sea areas necessary for the installation of plants for the production of energy from renewable sources that are required in order to meet their national contributions towards the 2030 renewable energy target in accordance with Article 3 of this Directive. Such areas shall be commensurate with the estimated trajectories and total planned installed capacity by renewable energy technology set in national energy and climate plans of Member States, as updated pursuant to Article 14 of Regulation (EU) 2018/1999.

(2) When identifying the areas referred to in paragraph 1, Member States shall take into account:

(a)the availability of the renewable energy resources and the potential for renewable energy production of the different technologies in the land and sea areas;

(b)the projected energy demand; 

(c)the availability of relevant grid infrastructure, storage and other flexibility tools or the potential to create such grid infrastructure and storage.

(3) Member States shall favour multiple uses of the areas identified as a result of the obligation in paragraph 1.’

(5) The following Article 15c is inserted:

‘Article 15c
Renewables go-to areas

(1) By [2 years after the entry into force], Member States shall adopt a plan or plans designating, within the areas referred to in Article 15b(1), renewables go-to areas for one or more types of renewable energy sources. In that plan or plans, Member States shall:

(a)Designate sufficiently homogeneous land and sea areas where the deployment of a specific type or types of renewable energy is not expected to have significant environmental impacts, in view of the particularities of the selected territory. In doing so, Member States shall:

·give priority to artificial and built surfaces, such as rooftops, transport infrastructure areasparking areas, waste sites, industrial sites, mines, artificial inland water bodies, lakes or reservoirs, and, where appropriate, urban waste water treatment sites, as well as degraded land not usable for agriculture;

·exclude Natura 2000 sites and nature parks and reserves, the identified bird migratory routes as well as other areas identified based on sensitivity maps and the tools referred to in the next point, except for artificial and built surfaces located in those areas such as rooftops, parking areas or transport infrastructure.

·use all appropriate tools and datasets to identify the areas where the renewable energy plants would not have a significant environmental impact, including wildlife sensitivity mapping.

(b)Establish appropriate rules for the designated renewable go-to areas, including on the mitigation measures to be adopted for the installation of renewable energy plants, co-located energy storage facilities, as well as assets necessary for their connection to the grid, in order to avoid or, if not possible, to significantly reduce the negative environmental impacts that may arise. Where appropriate, Member States shall ensure that appropriate mitigation measures are applied to prevent the situations described in Articles 6(2) and 12(1) of Directive 92/43/EEC, Article 5 of Directive 2009/147/EEC and Article 4(1)(a)(i) and (ii) of Directive 2000/60/EC. Such rules shall be targeted to the specificities of each identified renewable go-to area, the renewable energy technology or technologies to be deployed in each area and the identified environmental impacts. Compliance with such rules and the implementation of the appropriate mitigation measures by the individual projects shall result in the presumption that projects are not in breach of those provisions without prejudice to paragraphs 4 and 5 of Article 16a. Where novel mitigation measures to prevent as much as possible the killing or disturbance of species protected under Council Directive 92/43/EEC and Directive 2009/147/EEC, or any other environmental impact, have not been widely tested as regards their effectiveness, Member States may allow their use for one or several pilot projects for a limited time period, provided that the effectiveness of such measures is closely monitored and appropriate steps are taken immediately if they do not prove to be effective. .

Member States shall explain in the plan the assessment made to identify each designated go-to area on the basis of the criteria set out in point (a) and to identify appropriate mitigation measures.

(2) Before its adoption, the plan or plans designating renewables go-to areas shall be subject to an environmental assessment carried out in accordance with the conditions set out in Directive 2001/42/EC, and where applicable, if including artificial and built surfaces located in Natura 2000 sites, likely to have significant impacts in those sites, to the appropriate assessment in accordance to Article 6(3) of Directive 92/43/EEC.

(3) The plan or plans designating renewables go-to areas shall be made public and shall be reviewed periodically, at least in the context of the update of the national energy and climate plans pursuant to Article 14 of Regulation (EU) 2018/1999.’

(6) Article 16 is replaced by the following: 

‘Article 16
Organisation and main principles of the permit-granting process

(1) The permit-granting process shall cover all relevant administrative permits to build, repower and operate plants for the production of energy from renewable sources, co-located energy storage facilities, as well as assets necessary for their connection to the grid, including grid connection permits and environmental assessments where these are required. The permit-granting process shall comprise all procedures from the acknowledgment of the validity of the application in accordance with paragraph 2 to the notification of the final decision on the outcome of the procedure by the relevant authority or authorities.

(2) No later than fourteen days for plants located in go-to areas and one month for plants located outside of go-to areas, following the receipt of the application, the competent authority shall validate the application or, if the developer has not sent all the information required to process an application, request the developer to submit a complete application within fourteen days from this request. If the developer does not submit a complete application within this deadline, the competent authority may reject the application in written form. In the event of a rejection, the competent authority shall justify its decision. The developer may resubmit a new application at any point in time following such rejection. The date of the acknowledgement of the validity of the application by the competent authority shall serve as the start of the permit-granting process.

(3) Member States shall set up or designate one or more contact points. Those contact points shall, upon request by the applicant, guide through and facilitate the entire administrative permit application and granting process. The applicant shall not be required to contact more than one contact point for the entire process. The contact point shall guide the applicant through the administrative permit application process, including the environmental related steps, in a transparent manner up to the delivery of one or several decisions by the responsible authorities at the end of the process, provide the applicant with all necessary information and involve, where appropriate, other administrative authorities. The contact point shall ensure fulfilment of the deadlines for the permit-granting procedures set out in this Directive. Applicants shall be allowed to submit relevant documents in digital form. By [2 years from entry into force] Member States shall ensure that all procedures are carried out in electronic format.

(4) The contact point shall make available a manual of procedures for developers of renewable energy production plants and shall provide that information also online, addressing distinctly also small-scale projects and renewables self-consumers projects. The online information shall indicate the contact point relevant to the applicant's application. If a Member State has more than one contact point, the online information shall indicate the contact point relevant to the applicant's application.

(5) Member States shall ensure that applicants have easy access to simple procedures for the settlement of disputes concerning the permit-granting process and the issuance of permits to build and operate renewable energy plants, including, where applicable, alternative dispute resolution mechanisms.

(6) The deadlines laid down in Articles 16a, 16b and 16c shall apply without prejudice to judicial appeals, remedies and other proceedings before a court or tribunal, and to alternative dispute resolution mechanisms, including complaints procedures, non-judicial appeals and remedies, and may be extended for the duration of such procedures.

(7) Member States shall ensure that administrative and judicial appeals in the context of a project for the development of renewable energy production plant or its related grid connection, including those related to environmental aspects shall be subject to the most expeditious administrative and judicial procedure  that is available at the relevant national, regional and local level.’

(7) The following Article 16a is inserted:

Article 16 - a Permit-granting process in renewables go-to areas

(1) Member States shall ensure that the permit-granting process referred to in Article 16(1) shall not exceed one year for projects in renewables go-to areas. Where duly justified on the ground of extraordinary circumstances, that one-year period may be extended by up to three months. In such a case, Member States shall clearly inform the developer about the extraordinary circumstances that justified the extension.

(2) The permit-granting process for the repowering of plants and for new installations with an electrical capacity of less than 150 kW, co-located energy storage facilities as well as their grid connection, located in renewables go-to areas shall not exceed six months. Where duly justified on the ground of extraordinary circumstances, such as on grounds of overriding safety reasons where the repowering project impacts substantially on the grid or the original capacity, size or performance of the installation, that one year period may be extended by up to three months. Member States shall clearly inform the project developer about the extraordinary circumstances that justify the extension. 

(3) Without prejudice to paragraphs 4 and 5, by derogation from Article 4(2) of Directive 2011/92/EU, and Annex II, points 3(a), (b), (d), (h), (i), and 6(c) alone or in conjunction with point 13(a) to that Directive as far as this concerns renewable energy projects, new applications for renewable energy plants, except for biomass combustion plants, including the repowering of plants, in already designated renewables go-to areas for the respective technology, co-located storage facilities as well as their connection to the grid, shall be exempted from the requirement to carry out a dedicated environmental impact assessment under Article 2(1) of Directive 2011/92/EU, provided that these projects comply with the rules and measures set out in accordance with Article 15c(1), point (b). The exemption from the application of Directive 2011/92/EU above shall not apply to projects which are likely to have significant effects on the environment in another Member State or where a Member State likely to be significantly affected so requests, as provided for in Article 7 of the said Directive.

By derogation from Article 6(3) of Directive 92/43/EEC, the plants referred to in the first subparagraph, shall not be subject to an assessment of their implications for Natura 2000 sites.

(4) The competent authorities of Member States shall carry out a screening of the applications referred to in paragraph 3. Such screening shall aim to identify if any of such projects is highly likely to give rise to significant unforeseen adverse effects in view of the environmental sensitivity of the geographical areas where they are located, that were not identified during the environmental assessment of the plan or plans designating renewables go-to areas carried out in accordance with Directive 2001/42/EC and, if relevant, with Directive 92/43/EEC. The screening carried out for the repowering of projects shall be limited to the potential impacts stemming from the change or extension compared to the original project.

For the purpose of such screening, the project developer shall provide information on the characteristics of the project, on its compliance with the rules and measures identified according to Article 15c (1), points (b) and (c), for the specific go-to area, on any additional measures adopted by the project and how these measures address environmental impacts. Such screening shall be finalised within 30 days from the date of submission of the applications for new renewable energy plants, with the exception of applications for installations with an electrical capacity of less than 150 kW. For such installations and for new applications for the repowering of plants, the screening phase shall be finalized within 15 days.

(5) Following the screening process, the applications referred to in paragraph 3 shall be authorised from an environmental perspective without requiring any express decision from the competent authority, unless the competent authority adopts an administrative decision, duly motivated and based on clear evidence, that a specific project is highly likely to give rise to significantunforeseen adverse effects in view of the environmental sensitivity of the geographic area where they are located that cannot be mitigated by the measures identified in the plan or plans designating go-to areas or proposed by the developer for the project. Such decision shall be made available to the public. Such projects shall be subject to an assessment in accordance with Directive 2011/92/EC and, if applicable, to an assessment under Article 6(3) of Directive 92/43/EEC, which shall be carried out within six months following the screening decision.

(6) In the permit-granting process of the applications referred to in paragraphs 1 and 2, the lack of reply of the relevant administrative bodies within the established deadline shall result in the specific administrative steps to be considered as approved, except in those cases where the specific project is subject to an environmental impact assessment in accordance with paragraph 5. All resulting decisions will be publicly available.

(8) The following Article 16b is inserted:

Article 16 - b Permit-granting process outside renewables go-to areas

(1) Member States shall ensure that the permit-granting process referred to in Article 16(1) shall not exceed two years, for projects outside renewables go-to areas. Where duly justified on the grounds of extraordinary circumstances, that two-year period may be extended by up to three months. In such a case, Member States shall clearly inform the developer about the extraordinary circumstances that justified the extension.

(2) Where an environmental assessment is required under Directive 2011/92/EU or Directive 92/43/EEC, it shall be carried out in a single procedure that combines all relevant assessments for a given project. When any such environmental impact assessment is required, the competent authority, taking into account the information provided by the developer, shall issue an opinion on the scope and level of detail of the information to be included by the developer in the environmental impact assessment report, of which the scope shall not be extended subsequently. Where the specific projects have adopted appropriate mitigation measures, any killing or disturbance of the species protected under Article 12(1) of Directive 92/43/EEC and Article 5 of Directive 2009/147/EC shall not be considered deliberate. Where novel mitigation measures to prevent as much as possible the killing or disturbance of species protected under Council Directive 92/43/EEC and Directive 2009/147/EEC, or any other environmental impact, have not been widely tested as regards their effectiveness, Member States may allow their use for one or several pilot projects for a limited time period, provided that the effectiveness of such measures is closely monitored and appropriate steps are taken immediately if they do not prove to be effective. The permit-granting process for the repowering of projects and for new installations with an electrical capacity of less than 150 kW, co-located storage facilities as well as their grid connection, located outside renewables go-to areas shall not exceed one year including environmental assessments where required by relevant legislation. Where duly justified on the ground of extraordinary circumstances, this one-year period may be extended by up to three months. Member States shall clearly inform the developers about the extraordinary circumstances that justified the extension.

Member States shall facilitate the repowering of projects located outside go-to areas by ensuring that, if an environmental assessment for a project is required under the Union environmental legislation, such assessment shall be limited to the potential impacts stemming from the change or extension compared to the original project. ’

(9) The following Article 16c is inserted:

‘Article 16c
Permit-granting process for the installation of solar energy equipment in artificial structures

(1) Member States shall ensure that the permit-granting process referred to in Article 16(1) for the installation of solar energy equipment, including building-integrated solar installations, in existing or future artificial structures, with the exclusion of artificial water surfaces, shall not exceed three months, provided that the primary aim of such structures is not solar energy production. By derogation from Article 4(2) of Directive 2011/92/EU andAnnex II, points 3(a) and (b), alone or in conjunction with point 13(a) to that Directive, such installation of solar equipment shall be exempted from the requirement, if applicable, to carry out a dedicated environmental impact assessment under Article 2(1) of Directive 2011/92/EU.’

(10) The following Article 16d is inserted:

‘Article 16d
Overriding public interest

By [three months from entry into force], until climate neutrality is achieved, Member States shall ensure that, in the permit-granting process, the planning, construction and operation of plants for the production of energy from renewable sources, their connection to the grid and the related grid itself and storage assets are presumed as being in the overriding public interest and serving public health and safety when balancing legal interests in the individual cases for the purposes of Articles 6(4) and 16(1)(c) of Directive 92/43/EEC, Article 4(7) of Directive 2000/60/EC and Article 9(1)(a) of Directive 2009/147/EC.’

Article 2 - Amendment to Directive 2010/31/EU

Directive 2010/31/EU is amended as follows:

(1) The following Article 9a is inserted:

‘Article 9a
Solar energy in buildings

Member States shall ensure that all new buildings are designed to optimise their solar energy generation potential on the basis of the solar irradiance of the site, enabling the later cost-effective installation of solar technologies.

Member States shall ensure the deployment of suitable solar energy installations:

(a)by 31 December 2026, on all new public and commercial buildings with useful floor area larger than 250 square meters;

(b)by 31 December 2027, on all existing public and commercial buildings with useful floor area larger than 250 square meters; and

(c)by 31 December 2029, on all new residential buildings.

Member States shall define, and make publicly available, criteria at national level for the practical implementation of these obligations, and for possible exemptions for specific types of buildings, in accordance with the assessed technical and economic potential of the solar energy installations and the characteristics of the buildings covered by this obligation.

Article 3 -   Amendment to Directive 2012/27/EU 

Directive 2012/27/EU is amended as follows: 

(1) in Article 3, paragraph 5 is replaced by the following: 

‘5. Member States shall collectively ensure a reduction of energy consumption of at least 13 % in 2030 compared to the projections of the 2020 Reference Scenario so that the Union’s final energy consumption amounts to no more than 750 Mtoe and the Union’s primary energy consumption amounts to no more than 980 Mtoe in 2030.’ 

Article 4 
Transposition

(1) Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with Article 1, point (10), by [three months after the entry into force of this Directive] at the latest.

Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with Article 1, points (1), (2), (3), (4), (6), (8) and (9), and Article 3 by [one year after the entry into force of this Directive] at the latest.

Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with Article 1, points (5) and (7), and Article 2 by [two years after the entry into force of this Directive] at the latest.

They shall forthwith communicate to the Commission the text of those provisions.

When Member States adopt those provisions, they shall contain a reference to this Directive or be accompanied by such a reference on the occasion of their official publication. Member States shall determine how such reference is to be made.

(2) Member States shall communicate to the Commission the text of the main provisions of national law which they adopt in the field covered by this Directive.

Article 5 - Entry into force

This Directive shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.

Article 6 - Addressees

This Directive is addressed to the Member States.